Foreign Aided Project (EFAP)
An Asian Development Bank (ADB) Assisted Project namely ‘Sindh Flood Emergency Reconstruction Project (Emergency Flood Assistance Project (EFAP) is also included in ADP 2023-24 as an On-Going Scheme.
- Competent Forum ECNEC
- Date of approval 6th December, 2022
- Total Length 848.18 KMs
- Total Cost Rs.48400 Million (90.86% ADB Loan Rs.43974.9million , 9.14% Gos share Rs 4425.0 Million)
- Allocation(2023-2024) Rs. 1500 Million
- Status Pre-qualification Process completed. The bid opening was held on 12-10- 2023 and work will be started in Nov, 2023
New Sindh Secretariat Building No. 1, 3rd Floor, Opp: Income Tax Building, Shahrah-e-Kamal Atta Turk, Karachi, Sindh.
02199212992
09:00 A.M to 05:00 P.M