Projects
ADP
S.No Gen. Sr. No. /UID (If any) Name of Project (as per PC-1) Project Location Project Cost (Approved) Project Date Of Approval Project Target Date For Completion Project Status (Ongoing/Completed)
No project data available at the moment.
Non-ADP
S.No Name of Project Project Category Project Location Project Cost Project Start Date Project Completion Date (if Any) Project Status (Ongoing/Completed)
No project data available at the moment.

Please Note that the Project data mentioned in the above table is based on the last 10 years.

Projects Initiated On Public Private Partnership (PPP) Mode

Total 05 Projects (3 successfully completed).

EXECUTED PROJECTS

  • Hyderabad Mirpurkhas Dual Carriageway (HMDC) | Operational Since August, 2012.
  • lKarachi Thatta Dual Carriageway Project (KTDC) | Operational Since November, 2017.
  • Sir Aga Khan Jhirk Mulla Katiyar Bridge (JMK) | Operational Since February, 2017

ONGOING PROJECTS

  • Ghotki-Kandhkot Bridge Project (GKBP).
  • Link Road (M9-N5) Project | 90% construction work has been completed excluding interchange @ M9.

HYDERABAD MIRPURKHAS DUAL CARRIAGEWAY (HMDC)

  • Dual carriageway  |Between Hyderabad & Mirpurkhas
  • Concessionaire      | Deokjae Connecting Roads (Private) Limited
  • Project Length       | 58.7 km (including 8 Bridges & 62 Culverts)
  • Project Cost           | Rs. 6710.361 Million
  • Completion            | Operational Since August, 2012

KARACHI THATTA DUAL CARRIAGEWAY PROJECT (KTDC)

  • Dual carriageway   | Between Ghaggar Phatak & Thatta Bypass
  • Concessionaire       | KATCAM
  • Project Length        | 49.185 km (Including 15 Bridges)
  • Project Cost            | Rs. 8800.000 Million
  • Date of start           | May, 2015 
  • Completion             | November, 2017

SIR AGA KHAN JHIRK MULLA KATIYAR BRIDGE      (JMK)

 

  • Bridge Project    | Between Jhirk & TMK – Bathoro Road
  • Concessionaire   | Al-Jasr Pakistan (Pvt.) Ltd.
  • Project Length    | 25 km Road length and 1.2 km Bridge Length
  • Project Cost        | Rs. 4500.000 Million
  • Completion         | Operational Since February, 2017

GHOTKI – KANDHKOT BRIDGE PROJECT (GKBP)

 

  • Bridge Project   | 4 Lane Bridge over River Indus
  • Concessionaire   | Ghotki Kandhkot Road & Bridge Company (Pvt.) Ltd.
  • Project Length   | 35.441 km Road length (including 12.2 km Bridge Length and      4.45 km Thull Link Road)
  • Project Cost   | Rs. 31.952 Billion
  • Date of Commencement   | July 20th 2020
  • Date of Completion   | July 19th 2027
  • Concession Period     | 25 Years 
  • Status   | Approach roads 18 Kms constructed out of 18.70 kms

LINK ROAD (M9-N5) PROJECT

  • Link Road Project   | Link Motorway (M9) to National Highway (N5)
  • Concessionaire   | LRC (Private) Limited
  • Project Length   | 22 km (approx.), Four Lane Dual Carriageway
  • Project Cost   | Rs. 1966.700 Million
  • Status   | 95% work has been completed excluding the interchange @ M-9 (Work on Interchange at M-9 would be executed by NHA)